Entrance Sign:  Repair and repainting is complete as of 8/29/25.

Corrective building painting: Repainting of exterior walls affected by poor mix of paint should be completed by 09/12/25 at no cost to the community.

Window Washing: Will begin once exterior painting is complete.

Flood Remediation: Two remediation projects are being completed due to in-condominium water runnage.

EV Charging Stations: On August 21st we submitted a grant proposal to the Department of Energy for consideration to install up to 5 EV Chargings Stations. Response is expected aroung the end of November. Thank you Nate Kracht for all your hard work in completing this proposal!

We are obtaining estimates: 

1)  to create a community emergency evacuation access gate in the fence line at the end of E building.

2) to reassess roof lines to determine immediacy of replacement.

3) to complete painting of Private stalls, disability spaces and stall stripping.

 